2023 Street Recon - Tulip St/161st Ave (CP 21-39)
Update 9/22/23- The project is complete. Final quantities and payments are being squared away. A notice will be sent in the mail on October 18th inviting impacted properties to the public hearing on November 18th.
Update 8/7/23- The road will be stripped and seeding will be done this week.
Update 7/27/23- The wear course will be placed tomorrow.
Update 7/21/23- The wear course is scheduled to be paved next week Friday, July 28th.
Update 7/13/23- The gravel will be toleranced tomorrow and Saturday and are scheduled to pave the base course starting on Monday, July 17th. Backfilling curb and irrigation is tentatively scheduled the week of the 24th.
Update 7/7/23- Next week, the road will be toleranced and any access gravel will be hauled off. The base course will be placed late next week.
Update 6/30/23- New curb was installed this week. Next week, the curb will be back filled with top soil and the road will be graded.
Update 6/23/23- The road was reclaimed and curb was removed this week. Next week, new curb will be installed.
Update 6/16/23- Storm sewer was installed this week. Next week, the road will be reclaimed followed by the curb being removed.
Update 6/9/23- Storm sewer has been installed on the south end of Tulip St and 161st Ave. Next week, they will begin working on installing storm sewer on the north end of Tulip St and Valley Drive.
Update 6/2/23- Trees were cut down this week, and storm and silt fence will be put in the following week.
Update 5/9/23- Some trees will be removed before construction starts at the end of May.
Update 4/28/23- All storm sewer and some curb and gutter has been staked. Starting toward the end of May, staking will begin.
Update 4/14/23- Curb replacement, street, driveway and tree removals, and silt fence placement have been identified on the project.
Update 4/12/23- The construction contract has been awarded to North Valley Inc. Preconstruction meeting has been scheduled for April 24th. Schedule of construction will be determined at that time. After the preconstruction meeting, the project and contact information will be sent out to residents. Refer to this site for updates during the construction.
Some curb, driveways and street sections have been marked for removals during construction phase. Surveying will take place prior to the start of construction.
Each year the roadway segments that are in the most need of repair throughout the City are reconstructed as a portion of the City of Andover’s street reconstruction program. The street reconstruction projects are identified in the City’s Capital Improvement Plan. Scheduled for reconstruction in 2023 is Tulip Street from 157th Avenue to 161st Ave, and 161st Avenue from Tulip Street to Round Lake Boulevard (see attached location map) .
The project will consist of reclaiming the existing bituminous roadway, shaping the existing gravel, replacing segments of curb and gutter, minor storm sewer improvements / repairs, and constructing a new bituminous surface.
The project will be funded from the City’s Road & Bridge Fund, with 25% of the total street related project costs assessed to the benefiting properties as identified in the City’s Roadway Reconstruction Assessment Policy.
A neighborhood meeting was held with affected residents October 18, 2022. We anticipate that construction will begin in late April / early May of 2023, with the project being completed by late summer 2023.
For construction related questions please contact David Berkowitz at 763-767-5133 or Jason Law at 763-767-5130.